Subject: Interest to work Cheveron NNPC western Deita Project

Date: 07/26/03 at 12:08 AM
Posted by: Cheo Yew Kim
E-mail: cheoyewkim@hotmail.com
Message Posted:

CURRICULUM VITAE
A well established certified Welding Inspector with 20 years experience in Welding inspection in the field of onshore and offshore Piping, structural and Equipment fabrication.
PERSONAL DATA

Name : CHEO YEW KIM
I/C : 530110-01-5229
Date of Birth : 10th January 1953
Nationality : Malaysian
Postal Address : 24, Jalan Kancil 27,
Taman Scientex,
81700 Pasir Gudang, Johor Bahru,
Johor, West Malaysia.
Email Address : cheoyewkim@pd.jaring.my or cheoyewkim@hotmail.com
Contact No. : 607-289 2427 (Resident)
6012-7091798 (Mobile Phone) or
6012-7041716 (Mobile Phone)

SUMMARY OF WORKING & FIELD EXPERIENCE

25 years experience inspection in various positions in Quality assurance, Quality Control and Welding Inspection in the field of onshore and off shore Piping/Structural Construction.

Familiar with all International Codes of practice related to the design fabrication, maintenance of statutory equipment and standards with respect to welding inspection and QA/QC activity.

Quality auditing experiences, for example Quality Management Systems, Quality Plans, Quality Assurance/ Quality Control Procedures.

Performs inspections to ensure construction work confirms with engineering specifications and company engineering standards. Reviews design drawings, engineering specifications and QA/QC programs for compliance to Company standards. Reviews and monitors implementation quality of control programs developed by construction contractors.

Worked as a coordinator for client inspection and third party inspection.

Comprehensive knowledge of welding duplex stainless steel type 2205.

Comprehensive knowledge of on-stream and off-system inspection techniques and codes of practice for the inspection, of in-service oil and gas related equipment, i.e. the pressure envelope such as piping, pressure vessels, columns, heat exchangers, risers, offshore, onshore structures, Reactor and Tower etc.

Comprehensive knowledge of welding, welding techniques, all main Non-Destructive Testing Techniques and Inspection Techniques, such as Radiography Testing. Ultrasonic testing, Magnetic Practical Inspection, Liquid Penetrant Inspection, Coating/Painting, Mechanical testing, etc.

Comprehensive knowledge on the regulatory act, or similar legislation or standards such as Design Engineering Procedure’s standard drawing, etc.

PROFFESION CERTIFICATIONS
2002 : European Welding Inspection Specialist Diploma. (EWIS/GB/02494)

2002 : Technician Member of The Welding Institute.(Reg. No:2695)

Dec 2001 : Senior Welding Inspector, CSWIP 3.2 (Cert No 5829)

Nov 2000 : Radiographic Interpretation, CSWIP 3.4 (Cert No 3710/2)
: Group A, B, C, D
1989 : Ultrasonic Practitioner Level 1&2, Sirim

1988 : Quality Control of Fabricated Product, CSWIP.
1987 : Welding Inspection CSWIP 3.1


OTHER TECHINCAL TRAINING & SKILL
July 2002 : ISO 9000:2000 Series Auditor/Lead Auditor Course and sat for the IRCA

Jan 2002 : Microsoft Excel level 2 (Informatic JB)
Aug 2001 : Microsoft Access level 2 (Informatic JB)
Jul 2000 : Failure Analysis (MINT)
Oct 1990 : Defect Sizing on Ultrasonic (SIRIM)
Sept1990 : Welding of Corrosion Resistant Alloys Duplex Stainless Steel (EPMI) ,Esso
Production Malaysia Inc.
Sept 1989 : Radiographic Interpretation (UTM)
Oct 1988 : Quality Control of Fabrication Products, Welding Institute of Cambridge, UK
1969 to 1972 : Apprenticeship Training in General Mechanic.
SUMMARY OF POSITION HELD & PROJECT INVOLVED.
Oct 2002 to Dec 2002 : QA Field Specialist with SHELL CHINA
: Carried out audit work for East west Pileline in Shaanxi province audit of final documentation of completed project visited work site to audit on working procedure in welding and pipe field weld coating.

Mar 2001 to May 2002 : Piping QA inspector in SHELL EA Project.
: HALLIBURTON FAR EAST, SINGAPORE : Fit-up inspection, visual Inspection, follow up with engineering change and review of weld control summary.
: Control of welds distortion during shop fabrication, carry out line walk,
understand the welding detail of various type of design on pipe support and
prepare punch list for the completed packages.
: Viewing the radiograph for the whole project and other NDT related matter.

Jan to Feb 2001 : QA/QC Inspector in PTTEP, Thailand
: TOTAL ELF
: Carry out installation of sea line for phase 3B Bangkok Field. SL12 from WP4 to WP11 (4.375 km). SL11 from RP to WP 12(17.485 km).

Dec 1999 to Dec 2000 : QA Mechanical Inspector.
: Exxon Mobil, Jurong Island, Singapore.
: Undertake the daily routine plant inspection inclusive of all the radiographic
interpretation

June to Aug 1999 : QA Inspector in SIRRI Island, Iran
: TOTAL SIRRI
: Base in Iran for the construction and erection of water injection module for SIRRI Island.
: Involved in architectural, mechanical, piping and structural activity.

Jan to Mar 1999 : QA/QC Supervisor.
: TOTAL MYANMAR.
: Involved in the NAPTHA injection project.

June to Dec 1998 : QA/QC Supervisor.
: TOTAL MIDDLE EAST
: Involved in SIRRI A & E field Development Project.

Mar to May 1998 : QA/QC Coordinator.
: PLANT ENGINEERING CONSTRUCTION

Jan to Feb 1998 : QA/QC Supervisor.
: TOTAL THAILAND Offshore.
: Upgrading of BONGKUT FIELD.

Jun to Dec 1997 : QC Coordinator.
: NIPPON STEEL CORPORATION
: Involved in pipe laying project and installation of Riser, Jacket and module
for E.P.M.I.

Jan to Mar 1997 : Piping Supervisor.
: TOTAL THAILAND.
: Involved in WP9 and WP10 production platform.
: Daily inspections on all hold points, like Fit-up visual, Hydro test and final Dimension control Bangkok field, upgrading like installation, glycol generating, close drain drum and 3rd stage separator.

Sept 96 to Aug 97 : Welding Inspector.
: Oilfield Pipeline Inspection Sdn Bhd
: Involved for both onshore and offshore projects.
: Attached to NRS (Norwegian Rail System) as a construction supervisor for LRT-2 Remedial work. Involved with supervision of repairing, welding
work, QC and NDT project. Prepare daily report for submission to DOSH.

Oct 95 to Sept 96 : Site Supervisor cum QC Manager.
: Plant Engineering and Construction Sdn Bhd.
: Involved in Piping and Erection of Petrol Chemical Plant.

Mar to Oct 95 : Quality Control Inspector.
: Sembeth Singapore : Attached to Piping and Structural Discipline.

Jan 93 to Feb 95 : SSB Inspector
: Architectural discipline M1 and M3 Living quarters.
: Daily inspections of all hold point activities.
: Erection of ceiling, flooring furniture, panel and kitchen equipment.
: Fabrication of E11 and M1 DR Jacket Acting Senior Inspector in charge of piping and structural activities.

Sept 91 to 1992 : QA Inspector.
: Petronas Carigali.
: Involved in fabrication B.N.Q. Living quarters
: Carrying out inspection on piping and structural activities.

Sept 90 to June 91 : Welding Inspector.
: Sembawang Engineering.
: Lead inspector on the inspection of Duplex Stainless Steel. Carried out welding procedure test, welder qualification test, welding repair procedure.
: In charge of quality flow chart, like Fit-up inspection, visual inspection, N.D.T clearance and hydrostatic test.

Jun to Aug 90 : SSB Inspector.
: E 11 Truck Line Project.
: Supervised contractor daily fabrication activities and also inspected one unit of receiver and launcher.

Feb to Jun 90 : SBB Inspector.
: Offshore installation and hook up activities.
: Installed SJJT-B Jacket and Deck.
: Compression platform for BOKOR “A” and 4 numbers of Riser’s and Submerge Truck line at EWP.

Oct 89 to Jan 90 : SSB Inspector.
: Onshore at Lutong Crude Oil Terminal.
: Inspection of Duplex Ferretic Austenitic Flowlines at OEM Workshop.
: Performed facilities inspection within the refinery and MCOT; such as Fire Hydrant Line drain lines, Exchanger furnace.
: Verify W.P.S. submitted by contractor and witness, all welders and procedure tests.

Aug 88 : General Inspector.: EPMI.
: To perform hook up inspection for SELIGI D Production Module.
: Daily activities Co-ordinate contractor fabrication activities, witness all hold points inspection N.D.T. clearance stress reliving, and Hydrostatic Testing.

May to July 88 : Back to SSB Catory one program during this Phase, installed TEMANA “A” compression Module and pipeline, also installed BOK C Jacket deck and pipeline.

Nov 87 to Oct 88 : Senior Quality Inspector.
: AY Fabrication Yard.
: Responsible for the procedure and welder qualification for Seligi B and D Fabrication. Carried out all hold point inspection.

Mar 86 to Oct 87 : Quality Control Inspector.
: Malaysia Shipyard Engiineering
: In piping discipline. Involved in the fabrication of GUTONG B and C production module
: Daily duty material verification inspection, dimensional control N.D.T. clearance hydrostatic testing and post weld heat treatment during load out.
: Carry out level’s check and also final documentation and all weld andmaterial summary.

Mar 85 to Mar 86 : Project Superintendent.
: Wong Heng Engineering.
: Involved in the fabrication of 9 numbers of storage tank of various sizes, install one unit of loading and unloading gantry, warehouse, guardhouse and
administrative building for Petronas Dagangan, Teluk Sepangar, Kota Kinabalu.

Jan 81 to Dec 84 : Project Supervisor.
: Wah Chang International Sdn Bhd
: Project under taken installation of Petronas Aviation Depot, at Kota Kinabalu.
: Laying 18” Submarine line at Petronas Mini Refinery, Paka.
: Laying 18” diameters underground line at Subang Airport Air Cargo Apron.

Dec 80 to Jan 81 : Senior Facilities Technician
: Motorola Semi Conductor
: Carry out daily maintenance work in the Plant.

Jan 74 to Dec 76 : Technician.
: Shell Refinery.
: Received in house training from the various departments.
: Training on reading at Blue Print welding symbol and actual construction work in the plant.
: Learned to operate the various type of machine in the workshop.
: Training on the various equipment in the plant, compressor, various types of : pump, heat exchanger, tower, cooler.

Jan to Dec 73 : Mechanical Fitter.
: Federal Land Development Authority.
: Involved in the General Plant improvement, project work attendance for breakdown in all ancillary plants including water treatment, compressor house and boiler house.
Jan 69 to Dec 72 : Mechanical Apprentice.
: Pamol Estate.
: Received formal training in Industrial Training Institute in Kuala Lumpur to become a General Mechanic.